Blackrock Silver Hires NewFields for Tonopah West Permit Work

Blackrock Silver hired NewFields to prepare permit designs for an exploration decline, test mining and a 50,000-tonne bulk sample at its Tonopah West project in Nevada.
Blackrock Silver Corp. (TSX: BRC) has hired NewFields Mining Design & Technical Services to prepare construction-level designs supporting a proposed 50,000-tonne bulk sample at Tonopah West in Nevada. The assignment advances the engineering needed for permit applications, rather than authorizing the underground work itself.
The agreement, signed through wholly owned Nevada subsidiary Blackrock Gold Corp., covers an exploration decline—an access tunnel—along with test mining and bulk-sample extraction. Blackrock expects the designs to be completed by year-end, establishing a near-term engineering milestone for the silver and gold project in Nye and Esmeralda counties.
Design package covers access, rock storage and site support
NewFields, based in Englewood, Colorado, will prepare designs for Tonopah West’s Water Pollution Control Permit and Nevada Reclamation Permit. Its scope also includes a tie-in to US Highway 95 and access to the project, according to Blackrock’s announcement carried by INN Precious Metals.
The surface work is a material part of the assignment. NewFields will design facilities for placing silver- and gold-bearing rock and associated waste rock at the surface, as well as facilities supporting technical personnel, construction and contractors. The proposed underground program therefore requires designs not just for reaching the rock, but also for handling the material once it is brought out.
That breadth makes the contract more than an underground-access design exercise. Highway access, surface material placement and support facilities are all included in the same engineering scope as the permit-related work. Those elements connect the proposed extraction program to the physical arrangements needed to carry it out.
Year-end target is for designs, not permit approval
NewFields will coordinate with Blackrock’s environmental adviser, Trinity Consultants, formerly WestLand Resources, to keep the engineering work, applications and submissions complete and consistent. That coordination links the construction plans with the environmental documentation required for the permitting process.
Blackrock anticipates submitting the designs to the Bureau of Mining Regulation and Reclamation, part of Nevada’s environmental regulator. The year-end target applies to completing the designs; it is not a deadline for regulatory approval or a start date for test mining.
The distinction matters for assessing progress at Tonopah West. Hiring the engineering contractor gives Blackrock a defined path toward preparing the applications, but the Water Pollution Control Permit and Nevada Reclamation Permit remain approval steps ahead of the proposed work. The next concrete milestone is completion of the design package and its submission for regulatory consideration.
Key facts
- Company: Blackrock Silver Corp. (TSX: BRC)
- Proposed bulk sample: 50,000 tonnes at Tonopah West, Nevada
- Engineering contractor: NewFields Mining Design & Technical Services
- Design target: Year-end completion, followed by regulatory submission