China Gold Reopens CSH Pit With Annual Target Intact

China Gold International resumed open-pit mining at its CSH mine in early October after a nearly five-month shutdown, maintaining its 2026 target of 70,732 to 83,592 ounces of gold.
China Gold International Resources (TSX: CGG; HKEX: 2099) has reopened its Chang Shan Hao gold mine’s open pit in Inner Mongolia without cutting its annual production target. The nearly five-month interruption stopped mining, but not processing—a distinction that helps explain how the company maintained its outlook.
Fresh ore extraction resumed in early October following repairs and regulatory filings. CSH’s processing plant had continued treating existing low-grade stockpiles while the pit was closed, preserving gold production during the interruption, according to Mining.com.
Stockpiles support the unchanged gold target
China Gold still expects CSH to produce between 70,732 and 83,592 ounces of gold in 2026. That range remains below the mine’s 2025 output of 96,816 ounces, so maintaining guidance does not mean restoring last year’s production level.
The operating history during the closure matters more than the shutdown’s duration alone. Because the plant remained active, the restart does not require the mine to recover an equivalent period of completely lost gold production. Stockpiled ore supplied the processing operation while access to newly mined material was interrupted.
With mining back in operation, China Gold plans to blend fresh ore with stockpiled material to keep delivery volumes and processing grades stable. The remaining production schedule therefore depends on coordinating pit output with the stockpile feed, rather than simply reopening the excavation area.
The unchanged forecast reflects management’s expectation that this combination can support the annual range. It is not an increase in guidance, and the restart itself does not establish that the target has already been secured.
Slope repairs underpin the return to mining
The shutdown began on May 22, 2026, after localized slope instability. No casualties or equipment losses were reported. China Gold commissioned geotechnical assessments to develop a remediation plan before bringing the pit back into service.
Work completed by the end of September included restoring roads, clearing loose material and rocks, reinforcing the landslide body and installing drainage systems. Ongoing slope monitoring was also part of the response.
The mine met the safety standards required to resume normal operations, and the company completed filings with emergency management authorities. Continued safety-risk controls remain part of its production scheduling for the rest of 2026, making slope management an operating requirement beyond the initial reopening.
CSH is not China Gold’s only producing asset. Its Jiama copper-gold polymetallic mine in Tibet produced 70,883 tonnes of copper and 61,218 ounces of gold in 2025, giving the company exposure to both metals alongside CSH’s gold output.
China Gold shares were up 2.4% at C$33.03 in Toronto by midday Tuesday, October 27, valuing the company at C$13 billion, or US$9.2 billion.
Key facts
- Mine restart: CSH open-pit operations resumed in early October after a nearly five-month shutdown.
- 2026 gold guidance: Unchanged at 70,732–83,592 ounces for CSH.
- Processing continuity: The plant continued operating on low-grade ore stockpiles during the pit shutdown.
- Toronto shares: TSX: CGG — C$33.03, up 2.4%, by midday October 27, 2026.