Contango Tops Drill Plan as Manh Choh Output Faces Pressure

Market Data by TradingView
Contango Tops Drill Plan as Manh Choh Output Faces Pressure

Contango Silver and Gold completed 56,492 meters of drilling at Kitsault against a 40,000-meter plan while guiding toward the lower end of its 2026 gold-equivalent production expectations.

Contango Silver and Gold Inc. (NYSE American: CTGO; TSX: CTGO) exceeded its Kitsault drilling target while staying on budget, but its producing Manh Choh operation faces a less favorable near-term outlook. Rain disrupted processing, higher reagent consumption added costs, and the company now expects production toward the lower end of its 2026 guidance.

The contrast separates progress on future projects from current operating performance. Kitsault assays are still pending, while Manh Choh’s deferred processing and cost pressures will feature in third-quarter financial results scheduled for mid-November, according to the company’s update carried by INN Precious Metals.

Manh Choh processing shifts into November

The third Manh Choh processing campaign of 2026 ran from August 20 through September 24, ending earlier than planned because of persistent above-average rainfall. Ore left from that campaign is now scheduled for processing during the fourth campaign, which is due to begin in November.

Mill modifications to accommodate higher copper and sulfide content increased consumption of processing chemicals, or reagents. Those costs, together with higher diesel costs and the processing delays, mean third-quarter unit cash costs are expected to resemble those of the second quarter rather than improve.

Contango pointed to the lower end of its 2026 production guidance of 40,000 gold-equivalent ounces attributable to its 30% stake in the Peak Gold joint venture. KG Mining (Alaska), an indirect subsidiary of Kinross Gold, owns the remaining 70% and operates the venture.

The company also said it had removed its hedges. That leaves it more directly exposed to gold-price movements, but does not remove the operating pressures from weather, fuel and ore-processing requirements.

Kitsault’s larger program awaits assay results

At Kitsault in northwest British Columbia, Contango completed 56,492 meters across 152 drill holes, compared with the original 40,000-meter plan. Chief Executive Rick Van Nieuwenhuyse said the company delivered roughly 40% more drilling on budget.

The company attributed the additional work to better rig productivity, lower drilling costs per meter and fewer weather or mobilization delays. The program ended October 15 and covered extensions of known high-grade zones, drilling intended to improve confidence in existing resources, and targets identified during 2025.

More completed drilling does not yet establish a larger mineral resource. Laboratory results are expected over the next two to three months, following review and validation. Those results are intended to feed a resource estimate in the first half of 2027, following the estimate released September 22, and then an Initial Assessment later in 2027.

Johnson Tract advances as Lucky Shot drilling expands

Johnson Tract’s infrastructure work moved ahead of schedule and came in under budget. Contango completed a 2.6-mile access road connecting the existing camp with the proposed underground entrance, along with a staging area at that entrance.

Budget efficiencies also allowed construction of a camp pad originally scheduled for 2027. A winterized, 60-person camp is targeted for construction in 2027 to support year-round work. The access improvements prepare the site for an underground exploration tunnel scheduled to begin that year, while environmental studies continue to support permitting.

At Lucky Shot, drilling began October 22 from the 2070E drift, an underground passage, to test the eastern extent of the vein system. The program calls for 3,650 meters across 42 holes. A second rig is scheduled to start from the 2300E drift on November 15, with 5,320 meters across another 42 holes planned.

Both rigs are expected to finish in early 2027. Before then, Contango expects fourth-quarter assay releases from the completed Coleman surface program and KM vein underground drilling. Those results, alongside Kitsault assays, will begin to show what the expanded fieldwork delivered beyond additional drilling meters.

Key facts

  • Listings: NYSE American: CTGO; TSX: CTGO
  • Kitsault drilling: 56,492 meters completed against 40,000 meters planned, on budget
  • Production outlook: Lower end of 2026 guidance of 40,000 attributable gold-equivalent ounces
  • Next financial update: Third-quarter 2026 results scheduled for mid-November

Sources

Photo: analogicus · Pixabay Content License — source

Newsletter signup
Free newsletter
Mining Stocks in your inbox

Our picks and analysis on gold, silver, uranium, lithium and critical minerals.

Free. Unsubscribe from any email. See our privacy policy.