I-80 Gold’s Nevada Staffing Gaps Put Output at Risk

Market Data by TradingView
I-80 Gold’s Nevada Staffing Gaps Put Output at Risk

I-80 Gold expects annual production in the lower half of its 40,000–50,000-ounce forecast as worker turnover delays access to high-grade ore in Nevada.

I-80 Gold (TSX: IAU; NYSE: IAUX) is keeping its annual production forecast at 40,000–50,000 ounces, but staffing problems at Granite Creek and a processing change at Archimedes now point to output in the lower half of that range.

The immediate challenge is turning available ore into production while preserving a larger expansion schedule. The company still targets annual gold output of 150,000–200,000 ounces starting in 2028, with production mining at Archimedes and refurbishment of the Lone Tree processing plant remaining on schedule.

Shares fell 2.9% to $1.88 in Toronto trading Tuesday morning, according to The Northern Miner. The operational setbacks come as higher labor costs consume part of Lone Tree’s project contingency, although management has not changed the plant’s restart timetable.

Granite Creek needs workers, not more mining areas

Worker turnover at Granite Creek delayed access to high-grade ore. Chief operating officer Paul Chawrun said contractor staffing had returned to previous levels after the contractor’s compensation structure was adjusted. Restoring headcount addresses the immediate shortage, but the production outlook still reflects the lost mining time.

An Oct. 26 note from SCP Resource Finance put the contractor workforce at about 100 employees against a target of roughly 120, amid strong competition for skilled workers in northern Nevada. The mine had enough working areas to support higher output; labor availability and the speed of the mining cycle were the constraints.

Water management adds another limit to the ramp-up. Deeper pumping wells and expanded treatment capacity are expected to help, SCP said. Meanwhile, Granite Creek’s September feasibility study raised projected life-of-mine all-in sustaining costs—a broad measure of production and sustaining investment costs—42% to US$2,273 per ounce.

Archimedes presents a different timing issue. The company plans to place oxide ore on the existing Ruby Hill leach pad rather than sell it to a third party. That shifts recognition of some production into the first quarter of 2027 without changing the planned year-end start of production mining.

Lone Tree’s contingency absorbs higher labor costs

Lone Tree is central to the expansion because it would let I-80 process its own refractory ore, whose gold is trapped in sulphide minerals and requires additional treatment. Bringing that work in-house would retain more of the margin currently paid to outside processors.

First gold remains targeted for the fourth quarter of 2027, following a refurbishment budgeted at about US$430 million. Labor costs are running 5%–10% above initial estimates but remain within contingency.

National Bank Financial analyst Don DeMarco said about 44% of capital had been committed and 20% of contingency drawn, compared with roughly 10% of contingency cited in the previous month’s development update. That leaves the schedule intact while reducing the reserve available to absorb further overruns.

Contract payments are occurring four to five months after commitments rather than the originally assumed 30 days, pushing spending into 2027, DeMarco said. The timing defers cash outflows; it does not remove the underlying project obligations.

Cash supports construction as operating losses widen

I-80 ended September with US$411.4 million in cash and cash equivalents, down from US$464.6 million three months earlier. National Bank Financial estimated potential liquidity of roughly US$620 million, but that includes a conditional US$100-million expansion of a gold-prepayment arrangement and about US$109 million from warrant exercises. Those sources are distinct from cash already held.

Third-quarter production fell 6% to 11,685 ounces. Stronger gold prices helped revenue edge higher to US$32.7 million, but the net loss widened to US$48.4 million from US$41.9 million as development and exploration expenses increased.

The company has also moved Mineral Point ahead of the Granite Creek open pit and Cove underground project in its development sequence, concentrating spending on its largest growth project. Archimedes and Mineral Point studies are now expected in the second half of 2027 rather than around midyear. DeMarco maintained his outperform rating and $4 target, judging development funded and on schedule despite the near-term production weakness.

Key facts

  • Annual production outlook: 40,000–50,000 ounces, with output expected in the lower half.
  • Toronto share price: TSX: IAU — $1.88, down 2.9%, Tuesday morning, Nov. 3, 2026.
  • Lone Tree restart: First gold targeted for Q4 2027; refurbishment budget about US$430 million.
  • Cash balance: US$411.4 million as of Sept. 30, 2026.

Sources

Photo: Momentmal · Pixabay Content License — source

Newsletter signup
Free newsletter
Mining Stocks in your inbox

Our picks and analysis on gold, silver, uranium, lithium and critical minerals.

Free. Unsubscribe from any email. See our privacy policy.