PLS Commits $150 Million to Fortescue Power Connection

A detailed view of a metalwork workshop showcasing tools, machinery, and steel bars.
A detailed view of a metalwork workshop showcasing tools, machinery, and steel bars.

PLS has signed a 20-year agreement with Fortescue for at least 325 gigawatt-hours of electricity annually at Pilgangoora, targeting operating-cost savings of approximately $15–20 per tonne.

PLS plans to invest approximately $150 million in power infrastructure to connect its Pilgangoora lithium operation in Western Australia to Fortescue’s electricity network, seeking lower operating costs as it expands the mine. Electricity supply is targeted to begin in 2029 under a newly signed 20-year power purchase agreement.

The contract, executed by PLS subsidiary Pilgangoora Operation and Fortescue subsidiary FMG Clean Energy, covers at least 325 gigawatt-hours annually. That supply is intended to support forecast demand under Pilgangoora’s P2000 operating model, according to Australian Mining.

The investment trades an upfront infrastructure commitment for anticipated long-term operating savings. For Fortescue, it also establishes an external customer for a power network originally developed to serve its own operations.

Power savings would improve P2000 expansion economics

PLS expects the arrangement to cut forecast unit operating costs by approximately $15–20 per tonne relative to the recently approved P2000 expansion’s 10-year average operating-cost estimates. The comparison is against the expansion plan, rather than a reported reduction in current operating costs.

Managing director and chief executive Dale Henderson said the agreement would improve the expansion’s economics beyond those outlined when the company made its final investment decision. Lower power costs would strengthen Pilgangoora’s ability to operate through lithium market cycles, while the connection would provide capacity for further growth.

PLS expects to spend the approximately $150 million between the 2026–27 and 2028–29 financial years. The spending therefore comes ahead of the targeted supply start, making construction delivery an important part of achieving the projected operating benefits.

The project involves approximately 25 kilometers of new 220-kilovolt transmission infrastructure connecting Pilgangoora with Fortescue’s Turner River solar farm. PLS will fund and own around 20 kilometers of that connection.

Grid capacity extends beyond the expansion’s needs

The network will have capacity exceeding 100 megawatts, allowing it to accommodate potential developments including underground mining and fleet electrification. Those possibilities give the infrastructure a role beyond supplying the planned P2000 operating model, although they are not commitments to undertake those developments.

PLS also expects the arrangement to reduce Pilgangoora’s power-related emissions intensity by up to 80% from its 2022–23 baseline by 2030. That target concerns emissions associated with power, not an equivalent reduction across every source of emissions at the operation.

PLS will become Fortescue’s first external Green Grid customer. Fortescue chief executive Dino Otranto said the agreement would create a long-term revenue stream and described a pipeline of other prospective customers across the Pilbara. This contract establishes that external supply business; further customers would extend it.

The agreement remains subject to conditions, including construction arrangements and regulatory approvals. PLS will also retain and expand its on-site generation to manage supply interruptions, meaning the grid connection will supplement rather than eliminate the operation’s need for backup power.

Key facts

  • Contract: 20 years, covering at least 325 gigawatt-hours annually
  • Infrastructure investment: Approximately $150 million across financial years 2026–27 to 2028–29
  • Expected operating savings: Approximately $15–20 per tonne against P2000’s 10-year average cost estimates
  • Supply target: 2029 start, subject to conditions including construction arrangements and regulatory approvals

Sources

Photo: Bram van Egmond · Pexels Licence — source

Newsletter signup
Free newsletter
Mining Stocks in your inbox

Our picks and analysis on gold, silver, uranium, lithium and critical minerals.

Free. Unsubscribe from any email. See our privacy policy.